Wednesday, September 29, 2010

Moving Forward On a Bright Sunny Day

We are happy to report that with the sun comes our new floor.  At 7:00 AM this morning the contractor arrived, by the time we say our tefilah upon exiting from the sukkah we expect the floor and the steps to the basement to be finished......................

7am -- Sun is shining, bring with it the opportunity to work on our new floor.
At work
work continues on floor



Steps to the basement visible 

Friday, September 17, 2010

Because you asked---Seating Capacity

Q: What is the seating capacity of the new building?


The new building's dimensions are 42' x 80'. In addition to the sanctuary, on the main floor there will be a new men's room, a new coat room and new lobby. We currently estimate seating capacity to be 250-300 persons. The final count will be determined by several factors including the size of and location of the bimah as well as the ultimate type and size of the seating we use.

Sunday, September 12, 2010

UPDATE: Construction Update (Sep.12.10)

We hope you enjoyed what was, G-d willing, ECDP's last Rosh HaShana in our existing sanctuary.


The steel, joists and decking have been completed and the steel for the stairs is partially in place. Before Yom Kippur we intend, with G-d's help, to finish the stairs, complete the deck edging that forms the pan for the concrete and then pour concrete for the deck. 


The subsequent steps relate to the roof:  we will locate the openings for the skylights, add the curbs and install the supports for air conditioning and heating units that will be mounted on the roof. 


Look for pictures and more updates later this week.


This is an exciting time for ECDP and our entire community. If you would like to become a member or pledge in support of our building campaign please click on the links to the left to offer your support.  Dedications have been coming in-- please visit http://ecdpdedications.blogspot.com for details.